Return to Headlines

Velocity Learning Center (VLC) Building Update

Work on the new Velocity Learning Center (VLC) building continued this week as contractors have the steel under structure of the building fully assembled on a concrete pad that was recently poured around plumbing and electrical rough-ins. Presently, the building is ready for roof and siding panels, already on site. Once the panels are in place, windows and doors will be installed and the building will be insulated. Work on the interior of the building is slated to begin over the summer as VLC Director Jeff Smith and his staff are set to begin classes in the new facility next academic year.

 

 

 

Update on interior and exterior building progress

Interior work progress Alternative Learning Program building     Photo of the Exterior of the ALP building at Madison High School

Photo of Alternative Learning building construction       Photo of Alternative Learning building       Photo Alternative Learning building        Photo of Alternative Learning building